NOTICE OF ROAD CONSTRUCTION 5th & A Street
PLEASE BE ADVISED…Road Construction is set to begin on Thursday, October 16, 2025 on the 5th & A Street Pedestrian and ADA Improvement Project.
Tentative Construction Schedule:
Demo corner ramps, Demo for Cross Corner Culvert 10/16/2025 – 10/17/2025
Dig out A St & place base 10/17/2025
Set-up & Pour back corner ramps and Cross Corner Culvert 10/20/2025 – 10/24/2025
Grind 5th street, Finish grade on base, Pave 10/27/2025 – 10/31/2025
Striping 11/3/2025 – 11/7/2025
Final Cleanup & punchlist items 11/10/2025 – 11/19/2025
ROAD CLOSURES:
Please click below to see the road closure map and dates.
Traffic Control Plan